Palatka Elementary A - PK-6
Last Updated 06.13.2024
General Information
Design Manager: CRA Architects
Architect: KASPER
Contractor: Ausley Construction
Scope
1,055 Student Stations
Approximately 154,037 square foot
Location
156 Horseman Club Road, Palatka, FL 32177
Project Status
Sitework in Progress
Current Image
Project Image
DESIGN SCHEDULE | DAYS | DATE |
---|---|---|
Preconstruction Phase - Complete | April 9, 2024 | |
Finalize GMP with PCSD | March 4, 2024 | |
School Board Meeting to Approve GMP | March 14, 2024 | |
Notice to Proceed | March 15, 2024 | |
Building Permit - Received | April 1, 2024 | |
SJRWMD / DEP Permit - Received | April 9, 2024 | |
Construction Phase | 360 | March 18, 2024 |
Substantial Completion | 1 | July 15, 2025 |
Certificate of Occupancy | 1 | July 16, 2025 |
Puchlist / Closeout | 20 | July 17, 2025 |
Final Completion | 1 | August 14, 2025 |
Guaranteed Maximum Price : $60,292,595.00