Palatka Elementary A - PK-6

Last Updated 06.13.2024

General Information

  • Design Manager: CRA Architects

  • Architect: KASPER

  • Contractor: Ausley Construction

Scope

  • 1,055 Student Stations

  • Approximately 154,037 square foot

Location

  • 156 Horseman Club Road, Palatka, FL 32177

Project Status

  • Sitework in Progress

Current Image

Current Image

Project Image

Palatka Elementary A

DESIGN SCHEDULE

DAYS

DATE

Preconstruction Phase - Complete

April 9, 2024

Finalize GMP with PCSD

March 4, 2024

School Board Meeting to Approve GMP

March 14, 2024

Notice to Proceed

March 15, 2024

Building Permit - Received

April 1, 2024

SJRWMD / DEP Permit - Received

April 9, 2024

Construction Phase

360

March 18, 2024

Substantial Completion

1

July 15, 2025

Certificate of Occupancy

1

July 16, 2025

Puchlist / Closeout

20

July 17, 2025

Final Completion

1

August 14, 2025

Guaranteed Maximum Price : $60,292,595.00