Crescent City Jr./Sr. High - 7-12
Last Updated 06.13.2024
General Information
Design Manager: CRA Architects
Architect: CRA Architects
Contractor: Parrish McCall Constructors
Scope
1,320 Student Stations
Approximately 228,600 square foot
Construction will be phased and campus will remain occupied
Location
On existing High School Campus
Project Status
GMP 1 Approved by Board
NTP was issued on June 10, 2024
Current Image
Project Image
PROJECT SCHEDULE | DATE |
---|---|
Prepare Bid Scopes / Bid Packages | April 8, 2024 |
Advertise / Pre-qualification | April 15, 2024 |
Sub Bidding - Sub Bids Due | April 23, 2024 |
Sitework Revised Bid Date - TBD | May 7, 2024 |
Scope Out / GMP | May 16, 2024 |
Groundbeaking | May 17, 2024 |
Permitting - FPL, Site / SJRWMD, NEFEC (TBD) | May 29, 2024 |
GMP Approved at Board Meeting (ERP GMP 1) | June 6, 2024 |
NTP for Construction | June 10, 2024 |
Guaranteed Maximum Price Phase 1 : $1,912,907.00