Crescent City Jr./Sr. High - 7-12

Last Updated 06.13.2024

General Information

  • Design Manager: CRA Architects

  • Architect: CRA Architects

  • Contractor: Parrish McCall Constructors

Scope

  • 1,320 Student Stations

  • Approximately 228,600 square foot

  • Construction will be phased and campus will remain occupied

Location

  • On existing High School Campus

Project Status

  • GMP 1 Approved by Board

  • NTP was issued on June 10, 2024

Current Image

Current Image

Project Image

Project Image Coming Soon

PROJECT SCHEDULE

DATE

Prepare Bid Scopes / Bid Packages

April 8, 2024

Advertise / Pre-qualification

April 15, 2024

Sub Bidding - Sub Bids Due

April 23, 2024

Sitework Revised Bid Date - TBD

May 7, 2024

Scope Out / GMP

May 16, 2024

Groundbeaking

May 17, 2024

Permitting - FPL, Site / SJRWMD, NEFEC (TBD)

May 29, 2024

GMP Approved at Board Meeting (ERP GMP 1)

June 6, 2024

NTP for Construction

June 10, 2024

Guaranteed Maximum Price Phase 1 : $1,912,907.00