Crescent City Elementary - PK-6
Last Updated 06.13.2024
General Information
Design Manager: CRA Architects
Architect: CRA Architects
Contractor: Ajax and Armstrong Construction Companies
Scope
1,100 Student Stations
Approximately 145,501 square foot
New site at CR308 and Union Avenue
Location
New Site at CR308 and Union Avenue
Project Status
Construction Documents are Complete
GMP Pending Board Approval
Current Image
Project Image
DESIGN SCHEDULE | DAYS | DATE |
---|---|---|
100% Construction Documents | February 14, 2024 | |
Addendum 1 | March 15, 2024 | |
Addendum 2 | March 19, 2024 | |
Addendum 3 | April 4, 2024 | |
Bid Opening Group 1 | 1 | April 12, 2024 |
Bid Opening Group 2 | 1 | April 17, 2024 |
Bid Opening Group 3 | 1 | April 23, 2024 |
CM Finalize GMP | 14 | June 18, 2024 |
GMP Submitted & Tabled at School Board Meeting* | June 6, 2024 | |
GMP Approval at School Board Meeting | June 18, 2024 | |
Notice To Proceed** | TBD |